Sokkeldirektoratet

Almost half of Norwegian petroleum production will soon be run on power from shore

Forsideillustrasjon.png

6/26/2020 The companies are considering multiple electrification projects that could reduce emissions considerably.

Today, eight fields on the Norwegian shelf receive power from the Norwegian power grid. Decisions have also been made to supply another eight fields with power in this manner. This means that total CO2 emissions will be about 3.2 million tonnes lower per year than they otherwise would have been.

An additional six electrification projects are approaching an investment decision. If they are adopted, the avoided emissions will amount to approx. 4.9 million tonnes of CO2 per year. The Norwegian Petroleum Directorate's projections show that, at this point, more than 50 per cent of Norwegian petroleum production will be run on power from shore in the mid-2020s.

This emerges in a report the Norwegian Petroleum Directorate has prepared in collaboration with the Norwegian Water Resources and Energy Directorate (NVE), the Norwegian Environment Agency and the Petroleum Safety Authority. The report was submitted to Minister of Petroleum and Energy Tina Bru on Friday, 26 June.

"In a few years, power from shore can allow us to avoid CO2 emissions equivalent to ten per cent of total Norwegian greenhouse gas emissions. At this point, almost half of Norway’s oil and gas production will be running on power from shore", says Director General Ingrid Sølvberg.

"The companies are also working on several projects that could provide additional emission cuts beyond this".

Electrified fields and adopted projects

Today, the Troll, Gjøa, Ormen Lange, Valhall, Goliat and Johan Sverdrup fields have facilities supplied with power directly from shore. Vega is also operated with power from shore via its host installation Gjøa, and Hod via Valhall.

The Martin Linge field, which is under development, will be supplied with power directly from shore. The Edvard Grieg, Ivar Aasen, Gina Krog, Solveig and Hanz fields will receive power from the area solution on the Utsira High, which is part of the Johan Sverdrup field's second phase. The Duva and Nova fields will be operated with power from shore via Gjøa.

Power from shore to these 16 fields will lead to a reduction in CO2 emissions in Norway of 3.2 million tonnes per year, compared to what they would otherwise have been.

Power from shore in the planning phase

In addition to the 16 fields that are either operated with power from shore or where this has been adopted, six other projects have reached an advanced stage of the planning phase. These projects are on Troll B, Troll C, Oseberg Field Centre and Oseberg Sør, Sleipner and the Melkøya onshore facility.

An investment decision was made for Sleipner in May and the project is now under regulatory review. The project will also provide power from shore to the associated fields Gudrun, Sigyn, Gugne and Utgard.

The companies have reported data about the projects in the planning phase based on their studies. The report features calculated measure costs based on these data. The calculations show that the projects have a measure cost of below NOK 1500 per tonne of CO2.

The projects representing the greatest emission reductions are the Melkøya onshore facility, Troll B, Troll C, Oseberg Field Centre and Oseberg Sør.

The companies have reported that all the planned projects could be in operation from the mid-2020s.

Onshore power system

"Electrification of the shelf will have consequences for the power system both in the form of somewhat higher electricity prices and a need for increased investments onshore", says NVE Director General Kjetil Lund.

The six projects in advanced stages of the planning phase will increase annual power consumption in Norway by up to 4 TWh, or about 3 per cent per year.

The power from shore projects will lead to an increase in electricity prices in Norway, and smaller differences in electricity prices between the north and south in Norway. One important precondition is that the onshore power system can handle the increase in consumption, without this negatively affecting security of supply for existing customers.

Most power from shore projects that are under planning will require measures in the power grid. Electrification of the onshore facility on Melkøya requires the construction of a new power line.

It is also the case that, with the currently planned grid investments, the onshore facility on Melkøya, Troll B and C, Oseberg Field Centre and Oseberg Sør will have to be disconnected in strained situations in the power grid, and potentially use their own back-up power supply.

Update

The report is an update of the Power from shore report presented in 2008. Subsequent technology development has made power from shore projects more cost-effective. This is because it is now possible to transmit alternating current over greater distances, and thus reach more facilities.

A solution with alternating current does not require as much equipment on the platforms as direct current. Technology has also been developed for power from shore to floating production vessels (FPSOs).

 

Read more

Summary of the report "Power from shore to the Norwegian shelf", 2020 (in English)

The report "Power from shore to the Norwegian shelf", 2020 (in Norwegian)

 

Ingrid-Solvberg-OED-Kraft-fra-land-rapport-2020.jpg

The report is handed over to the Minister of Petroleum and Energy, Tina Bru. From left: Anne Vera Skrivarhaug (NVE), Tina Bru and Director general Ingrid Sølvberg.

Updated: 6/26/2020

Latest news

One company offered acreage for CO2 storage
6/13/2025 Today, Equinor Low Carbon Solution AS has been offered an exploration licence for CO2 storage in the North Sea.
Drilling permit for wellbore 7117/4-1
6/12/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 7117/4-1 in production licence 1238.
Full house to hear about new technology on the NCS
6/6/2025 Technology is one of the tools that can help generate additional values from the Norwegian continental shelf (NCS). At Technology Day new technology from different suppliers are presented.
New interactive map of deep sea data
6/5/2025 Today, the Norwegian Offshore Directorate is launching an interactive map, Deep Sea Surveys.
New Director of Offshore development and technology
6/5/2025 Producing the resources on the Norwegian continental shelf (NCS) so they generate the greatest possible values for society is an important driving force for the Norwegian Offshore Directorate's new director.
Proved suitable properties for CO2 injection and storage (9/6-1)
6/2/2025 A wildcat well drilled by Harbour Energy Norge and licensees in the “Havstjerne” storage project confirmed a reservoir that is suitable for injection and storage of carbon dioxide (CO2).
Oil discovery and dry well in the North Sea (31/4-A-23 F and 31/4-A-23 G)
5/28/2025 OKEA and the licensees in production licence 055 have discovered oil along the eastern flank of the Brage field.
Drilling permit for wellbore 35/11-31 S
5/23/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 35/11-31 S in production licence 090.
Drilling permit for wellbore 15/5-8 S and 15/5-8 A
5/22/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 15/5-8 S and 15/5-8 A in production licence 1140.
Production figures April 2025
5/20/2025 Preliminary production figures for April 2025 show an average daily production of 2 030 000 barrels of oil, NGL and condensate.