Plans to re-develop Tor

7/1/2019 On behalf of the licensees, operator Conoco Phillips has submitted a Plan for Development and Operation (PDO) for a re-development of the Tor field in the Greater Ekofisk area in the North Sea.

The field was in production from 1978 until it was shut down in 2015 when the installation reached the end of its lifetime. At shutdown, just 20 per cent of the resources in place had been produced.

The field will be re-developed by installing two new subsea templates tied into the Ekofisk Complex. The recoverable reserves are estimated at 10 million standard cubic metres of oil equivalents (Sm3).

The plan is to re-start production in late 2020. The total investment costs for the re-development are estimated at six billion kroner.

Updated: 7/1/2019

Latest news

Full house to hear about new technology on the NCS
6/6/2025 "Technology is one of the tools that can help generate additional values from the Norwegian continental shelf (NCS). At Technology Day new technology from different suppliers are presented."
New interactive map of deep sea data
6/5/2025 Today, the Norwegian Offshore Directorate is launching an interactive map, Deep Sea Surveys.
New Director of Offshore development and technology
6/5/2025 Producing the resources on the Norwegian continental shelf (NCS) so they generate the greatest possible values for society is an important driving force for the Norwegian Offshore Directorate's new director.
Proved suitable properties for CO2 injection and storage (9/6-1)
6/2/2025 A wildcat well drilled by Harbour Energy Norge and licensees in the “Havstjerne” storage project confirmed a reservoir that is suitable for injection and storage of carbon dioxide (CO2).
Oil discovery and dry well in the North Sea (31/4-A-23 F and 31/4-A-23 G)
5/28/2025 OKEA and the licensees in production licence 055 have discovered oil along the eastern flank of the Brage field.
Drilling permit for wellbore 35/11-31 S
5/23/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 35/11-31 S in production licence 090.
Drilling permit for wellbore 15/5-8 S and 15/5-8 A
5/22/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 15/5-8 S and 15/5-8 A in production licence 1140.
Production figures April 2025
5/20/2025 Preliminary production figures for April 2025 show an average daily production of 2 030 000 barrels of oil, NGL and condensate.
Oil discovery in the Norwegian Sea (6507/5-13 S and 6507/5-13 A)
5/20/2025 Aker BP ASA and its partners have made an oil discovery in the so-called E prospect near the Skarv field.
Drilling permit for wellbore 6406/11-2 S
5/19/2025 The Norwegian Offshore Directorate has granted Vår Energi ASA drilling permit for wellbore 6406/11-2 S in production licence 586.